Lindian Resources Logo
AU000000LIN6
A0LEHB
LIN.AX

Lindian Resources

Caricamento quotazioni...

Previsioni

Non sono disponibili dati degli analisti per questa azienda.


  • Lindian Resources acquires 100% of the SARECO processing plant in Kazakhstan

    Lindian Resources has purchased the remaining 49% of the hydrometallurgical SARECO plant in Stepnogorsk and is now sole owner. The total purchase price is US$20 million and includes two industrial facilities totaling 15,500 m² as well as additional land. Commissioning of the plant is planned for Q4 2026 and is intended to coincide with first production from the Kangankunde rare earth project; ANSTO validated a metallurgical NdPr recovery of 96%. Lindian secured financing through a A$100 million placement to complete the acquisition and generate initial cash flows. » Altro su de.investing.com


  • Lindian Resources starts construction in Malawi and moves into production phase

    Lindian Resources has initiated the transition from developer to producer: construction of the Kangankunde mine in Malawi is underway, first production is scheduled for Q4 2024, and all committed construction works are fully financed with AUD 191.5 million. The company owns a downstream SARECO plant in Kazakhstan (acquisition cost AUD 15 million) and a 15-year offtake agreement with Iluka for 6,000 tonnes of monazite concentrate per year. Management highlights low capital intensity (about AUD 25/kg NdPr capacity), strong economics (NPV AUD 831 million, IRR 80%) and a large resource with over 1 million tonnes of NdPr in the deposit. Stage 2 aims to expand capacity to 120,000 tonnes/year and is expected to receive the final investment decision by the end of 2024. » Altro su de.investing.com


  • Lindian Resources orders key long‑lead plant equipment and advances Kangankunde into execution

    Lindian Resources has moved the Kangankunde rare earths project into execution, placing procurement orders for critical long‑lead processing packages including the SAG mill, thickener and flocculation plant, shaking tables and belt filters while ramping earthworks and infrastructure. On‑site activity has scaled to more than 550 workers and the project has recorded 200,000 lost‑time‑injury‑free hours as construction, camp and admin works progress. The company reconfirmed its master schedule: process plant construction and mine stripping in February, first blast in April, grid power energisation in July and first ore feed and first concentrate targeted for November 2026. » Altro su finance.yahoo.com

Nel 2022, Lindian Resources ha già distribuito 0,0666 € di dividendi. L'ultimo pagamento è avvenuto a giugno 2022.

Dati finanziari dell'azienda

Nell'ultimo trimestre, Lindian Resources ha registrato ricavi pari a 0 € e un utile netto di -13,96 Mln €
(EUR) giugno 2026
YoY
Ricavi 0 -
Utile lordo -68,55K -
Utile netto -13,96 Mln -
EBITDA -5 Mln -

Dati fondamentali

Metrica Valore
Capitalizzazione di mercato
259,91 Mln €
Numero di azioni
1,12 Mld
Massimo/minimo a 52 settimane
0,63 € - 0,19 €
Dividendi No
Beta
-0,32
Rapporto P/E
-19,95
Rapporto PEG
0,17
Rapporto P/B
2,83
Rapporto P/S
0,00

Profilo aziendale

Lindian Resources Limited, insieme alle sue controllate, si occupa dell'esplorazione di giacimenti minerari in Africa. Esplora principalmente minerali auriferi, di bauxite e terre rare. La società si concentra sui progetti di bauxite Gaoual, Woula e Lelouma, situati nel nord-ovest della Guinea, in Africa occidentale, e sui progetti di bauxite Lushoto e Pare, situati in Tanzania. Lindian Resources Limited è stata costituita nel 1999 e ha sede a Perth, in Australia.

Nome
Lindian Resources
CEO
Robert Anthony Martin
Sede centrale Perth, wa
Australia
Sito web
Quotazione in borsa
29/02/2000
Dipendenti 2

Simboli di borsa

Borsa Simbolo
Australian Securities Exchange Ltd
LIN.AX
🍪

Parqet  usa i cookie. Scopri di più